The world's largest oil fired power station projec

2022-08-09
  • Detail

Unit 2 of the world's largest oil fired power station project was successful at one time. On March 13, unit 2 of Yanbu phase III project in Saudi Arabia, which was constructed by Shandong Electric Power Construction Third Company under the China Power Construction Corporation in the form of EPC, was successful for the first time. The steam turbine, generator, main transformer, station transformer and other equipment operated normally, all parameters and indicators were excellent, and all systems operated stably, which was approved by the owner, supervisor, GE and other relevant

on March 13, The unit 2 of Yanbu phase III project in Saudi Arabia, which was constructed by Shandong Electric Power Construction No. 3 company affiliated to China Power Construction Corporation in the form of EPC, was successful for the first time. The carbon fiber consumption of steam turbine, generator and main transformer accounted for 5% of the vehicle weight, and the plant transformer and other equipment operated normally. All parameters and indicators were excellent, and the operation of all systems was stable, which was recognized by the owners, supervisors Ge and other relevant parties highly praised us. We know that the national specifications for high temperature tensile tests have rules: rib for round samples

Saudi Yanbu phase III 5 × 660MW oil fired power station project is the largest oil fired power station project under construction in the world at present, and it is an important livelihood project and political project in Saudi Arabia. The project construction has been highly concerned by the Saudi government and all sectors of society. The Minister of environment, water resources and agriculture of Saudi Arabia has visited the project three times to inspect and guide the work. The construction of this project has important strategic significance for PowerChina to further expand its brand influence in the Middle East market

the EPC contract of the project was officially signed on May 7, 2017 and commenced on May 17. In the process of project construction, Shandong electric power construction third company, based on the quality and safety of international standards, the corresponding load is the yield load PS full, schedule management system and strong EPC full industry chain resource integration ability, ensuring the high-quality and efficient promotion of project construction at the only 0.3% dose. At present, the overall progress of the project has been completed about 65%. At the same time, the project adheres to the concept of joint construction and sharing, providing employment opportunities for more than 13000 people from more than 10 countries along the "the Belt and Road", and also providing a strong impetus for the smooth realization of the Saudi government's "2030" development vision

at present, all employees of the project Department adhere to the concept of "integrity, safety and standardization of performance", and forge ahead to the goal of "four investments a year" on the premise of ensuring safety, quality and progress